Procedure - Stage 2

Swimming Pool Removal - Stage 2 Featured Photos

The pool is filled in with materials that are contaminent free.

We provide copies of all vendors packing slips.

We use 3/4" crushed limestone gravel, sand and top soil.

Each layer of material is compacted to prevent future settling.

A good day at filling in a swimming pool would be 3 (three) loads of back-fill and all the material compacted - For proper compaction, this take time!

For Example: 16ft x 32ft pool would take approximately 200 yards of fill. That is 7 (seven) to 8 (eight) loads of material.
pool_removals_4014006.jpg pool_removals_4014005.jpg pool_removals_4014003.jpg pool_removals_4014002.jpg
About Us
Links
Procedure
Contact Us
Copyright (c) 2008 A-1 Pool Removals Inc. all rights reserved
Next Page
Previous Page
Return to Procedure Page
pool_removals_4014001.jpg
Home
Photo Gallery
Day 3 to 5 - The Fill In