Procedure - Stage 2
Swimming Pool Removal - Stage 2 Featured Photos
The pool is filled in with materials that are contaminent free.
We provide copies of all vendors packing slips.
We use 3/4" crushed limestone gravel, sand and top soil.
Each layer of material is compacted to prevent future settling.
A good day at filling in a swimming pool would be 3 (three) loads of back-fill and all the material compacted - For proper compaction, this take time!
For Example: 16ft x 32ft pool would take approximately 200 yards of fill. That is 7 (seven) to 8 (eight) loads of material.
About Us
Links
Procedure
Contact Us
Copyright (c) 2008 A-1 Pool Removals Inc. all rights reserved
Next Page
Previous Page
Return to Procedure Page
Home
Photo Gallery
Day 3 to 5 - The Fill In